Why this matters
An annual plan that lists everything anyone asked for is not a plan; it is a promise to do most of it late. The annual planning guide fixes objectives once a year and corrects the plan each quarter. The guide to prioritising work and capacity supplies the method underneath: score against objectives, size real capacity, fill it from the top and stop.
The theatre and its wish list
Lanternfield Playhouse is an invented regional theatre whose year runs from April. Its annual plan sets two objectives: more first-time bookers returning for a second show within the year, and more members of its Friends scheme. The marketing manager, a marketing officer and a half-time designer also run every show campaign, the season brochure and the monthly report, so projects compete for what is left.
The wish list, scored by the team
Impact and confidence on a scale of 1 to 3; effort in team days, estimated by the people who would do the work.
| Project | Objective | Impact | Confidence | Effort | Of which design | Notes |
|---|---|---|---|---|---|---|
| Post-show email journey for first-time bookers | Return visits | 3 | 3 | 15 | 3 | Piloted on one show last season |
| Pantomime early-bird campaign | Return visits | 2 | 3 | 10 | 4 | Pantomime goes on sale in July |
| Box office audience segmentation | Both | 2 | 2 | 12 | 0 | Unblocks the email journey and the Friends relaunch |
| Schools group bookings outreach | Return visits | 2 | 3 | 20 | 2 | Schools book in the summer term for the autumn |
| Friends membership relaunch | Friends | 3 | 2 | 30 | 8 | New tiers and benefits |
| Three-show pass | Return visits | 3 | 1 | 20 | 4 | No evidence yet; a small test version needs 8 days |
| Website rebuild | Both | 2 | 2 | 80 | 25 | Booking flow works; site looks dated |
| Rebrand | Neither directly | 1 | 1 | 60 | 30 | Requested by the chair of trustees |
| Podcast | Neither directly | 1 | 1 | 30 | 2 | |
| Short-video channel | Neither directly | 1 | 1 | 25 | 10 |
Capacity: about 137 team days a quarter, less 80 for recurring work and 15 held for urgent requests, leaves about 40 project days a quarter. In October to December the pantomime season doubles recurring work, leaving about 25. The designer has about 8 free days a quarter.
Scoring against capacity
- Objective fit first. A project that serves neither objective goes to the backlog, however popular.
- Rank by impact times confidence over effort, then apply judgement for deadlines and dependencies.
- Low confidence, high impact means test small. Commit a small version, not the full project.
- Check capacity by skill. Total days can fit while the designer is overloaded.
Task
- Remove the projects that serve neither objective and say where they go.
- Score the rest as impact times confidence, times ten, divided by effort, and rank them.
- Adjust the ranking for deadlines, dependencies and low-confidence projects.
- Lay the projects across the four quarters within total and design capacity.
- List what is left out of the year and why, and say how you would answer the chair about the rebrand.
- Name one KPIA metric tied directly to an objective. per objective that the quarterly reviews will track.
Worked answer
Ranking
| Project | Working | Score |
|---|---|---|
| Post-show email journey | 3 × 3 × 10 ÷ 15 | 6.0 |
| Pantomime early-bird | 2 × 3 × 10 ÷ 10 | 6.0 |
| Audience segmentation | 2 × 2 × 10 ÷ 12 | 3.3 |
| Schools outreach | 2 × 3 × 10 ÷ 20 | 3.0 |
| Friends relaunch | 3 × 2 × 10 ÷ 30 | 2.0 |
| Three-show pass | 3 × 1 × 10 ÷ 20 | 1.5 |
| Website rebuild | 2 × 2 × 10 ÷ 80 | 0.5 |
The rebrand, podcast and short-video channel serve neither objective and go to the backlog with that reason recorded. Segmentation scores below the email journey but moves to the front because two higher-value projects depend on it. The three-show pass has high potential impact and no evidence, so it enters as a small test. The website rebuild scores low for its size: the booking flow works, so its ROIProfit relative to cost. against the objectives is weak this year.
The roadmap by quarter
| Quarter | Projects | Team days | Design days |
|---|---|---|---|
| April to June | Segmentation 12, email journey 15, schools outreach first half 10 | 37 of 40 | 5 of 8 |
| July to September | Pantomime early-bird 10, schools outreach second half 10, Friends relaunch first half 15 | 35 of 40 | 8 of 8 |
| October to December | Friends relaunch second half 15, three-show pass test 8 | 23 of 25 | 6 of 8 |
| January to March | Read the pass test and scale it if it works 12, website scoping for next year 10 | 22 of 40 | 4 of 8 |
The final quarter is deliberately light: it absorbs any slip from the pantomime season and leaves room to scale the pass if the test succeeds. Schools outreach is split so that the summer-term booking window is met.
Left out of the year. The full website rebuild, replaced by scoping so next year's decision rests on evidence; the rebrand; the podcast; the short-video channel. For the chair, show where the rebrand would rank and what it would displace: the Friends relaunch and most of the designer's year. If the trustees still want it, the decision goes to whoever set the objectives, and the trade-off is recorded.
Measures. For return visits, the share of first-time bookers who book again within the year, read by quarter of first visit; a returning booker's LTVTotal value a customer brings over time. is what justifies the email journey. For Friends, net new members per quarter.
Common mistakes
- Planning to full capacity. Without the urgent-work buffer, the first press issue breaks the plan.
- Ignoring the designer. Total days fit long before design days do.
- Ranking by score alone. Dependencies and fixed selling windows move projects up or down.
- Not writing down what was cut. Unlisted projects return mid-year as urgent requests; the quarterly marketing planning playbook records them in the plan.